PERFORMANCE LIST
Projects, completed by MONTAGE COMPLECT ENGINEERING Ltd. in the field of power generation, chemical and cement industry, and non-ferrous metallurgy



No:
Project Name
Project Completed
Contractor
Investor
Gallery
1.
Erection of new cement mill and raw meal silos with the corresponding transport systems
September 2009 and in progress
Titan Zlatna Panega Cement AD
Titan Zlatna Panega Cement AD

2.
“FRP Stacks, Gas Ducts and Auxiliary Equipment for FGD Plants for Units 7 & 8 at TPP “Maritsa East 2” PLC – design, procurement of materials, fabrication and erection of steel structures and FRP elements
July, 2008 and in progress
TPP “Maritsa East – 2”
TPP “Maritsa East – 2”

3.
Engineering, Design and Completion, Including Design Works and Construction of Vessel Capacities, Design Works, Reconstruction&Repair Works to set Petroleum Stations, Property of the STATE AGENCY “STATE RESERVS AND WAR TIME RESOURCES” in Compliance with the Bulgarian and the European Legislation
December, 2007 and in progress
STATE AGENCY “STATE RESERVS AND WAR TIME RESOURCES”
STATE AGENCY “STATE RESERVS AND WAR TIME RESOURCES”

4.
Beli Izvor Capacity Increase Project - procurement of materials, fabrication and erection of steel structures for Roller Press Building and installation of technological equipment
November, 2007 – March, 2009
HOLCIM (BULGARIA) JSCo.
HOLCIM (BULGARIA) JSCo.

5.
Flue Gas Desulphurization Plant – TPP “Maritsa East – 2” -Prefabrication of steel structures for: stack support structure, ducts and absorbers – 2000 ton
September 2006 – December, 2008
I H I Japan
TPP “Maritsa East – 2”

6.
SRF Project – design works, procurement of materials, fabrication and erection of steel support structures and installation of equipment for belt conveyors – 500 ton
April – September, 2007
HOLCIM (BULGARIA) JSCo.
HOLCIM (BULGARIA) JSCo.

7.
Construction Works and Equipment Installation of Cement Kiln No: 5
June – December, 2006
TITAN ZLATNA PANEGA CEMENT JSCo.
TITAN ZLATNA PANEGA CEMENT JSCo.

8.
Project for Kiln Upgrading in the Cement Plant – Beli Izvor . Delivery of materials, prefabrication and construction of steel structures – 2500 ton
December, 2005 – August, 2006
HOLCIM (BULGARIA) JSCo.
HOLCIM (BULGARIA) JSCo.

9.
Flue Gas Desulphurization Plant – delivery of materials, prefabrication and construction of steel structures – TPP “Maritsa East – 3” – 4500 ton
2003 - 2006
CONSORTIUM DSD / RWE
“Energy Company – Maritsa Eeast 3” JSC

10.
Coal Powder Silo – supply of materials, prefabrication and construction – 180 ton
2002
HAIDELBERG CEMENT Zlatna Panega
HAIDELBERG CEMENT Zlatna Panega

11.
Construction of Technological Pipelines and Installation of Adjacent Equipment
2001 –2002
LURGI BISCHOFF Germany
UMICORE MED Pirdop

12.
Flue Gas Desulphurization Plant – delivery of materials, prefabrication and construction of steel structures 4500 ton
1999 –2002
KLOECKNER TESSAG INA /SHU Germany
National Electric Company TPP “Maritsa East – 2”

13.
Delivery, Prefabrication and construction of a Cement Kiln
1999
HAIDELBERG CEMENT Zlatna Panega
HAIDELBERG CEMENT Zlatna Panega

14.
Supply of materials and construction of reservoirs for sulfuric acid 1800 м3 - 2 pcs
1996 -1997
Plant for Non-ferrous Metals Plovdiv
Plant for Non-ferrous Metals Plovdiv

15.
Supply of materials and mounting of reservoirs for mazut 2000 м3 - 2 pcs.
1995
TPP “Bobov Dol”
TPP “Bobov Dol”

16.
“Reconstruction and modernization of urea tower” – supply of materials, prefabrication and erection of steel structures and installation of technological equipment
1992 –1993
HIMKO JSC Vratsa
HIMKO JSC Vratsa